Date format in FSM

  • September 25, 2023
  • 2 replies
  • 93 views

Forum|alt.badge.img+7

Is it possible to change the date format to not include time? For example we are trying to change the “Planned Start Date” for a task so that it only requires a data not a date and time.

Best answer by Shneor Cheshin

Hey @IGMIGMIMXMD 

Please note that after the changes the value is still saved as date/time in the DB.

You will need to

  • Change the custom metadata to be mask type of DATEONLY
  • Update the same in the UI designer

 

 

 

Result

 

Cheers!

View original

2 replies

Shneor Cheshin
Superhero (Employee)
Forum|alt.badge.img+28
  • Superhero (Employee)
  • 1143 replies
  • Answer
  • September 25, 2023

Hey @IGMIGMIMXMD 

Please note that after the changes the value is still saved as date/time in the DB.

You will need to

  • Change the custom metadata to be mask type of DATEONLY
  • Update the same in the UI designer

 

 

 

Result

 

Cheers!


Forum|alt.badge.img+7
  • Author
  • Sidekick (Customer)
  • 22 replies
  • September 26, 2023
IGMIGMIMXMD wrote:

Is it possible to change the date format to not include time? For example we are trying to change the “Planned Start Date” for a task so that it only requires a data not a date and time.

 

Brilliant, thanks for your help.


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings