Good day
I am having an issue with my Passive Preventative Maintenance task time commitments. When tasks are created from a contract they have two time commitments: one for now, and a second for a future time commitment. The task should be scheduled for the future time commitment, not for the “Now” time commitment. When removing the “Now” commitment, it also removes the tasks from PSO (which show all tasks, but as unallocated).
Is there a way to remove the time commitment that is scheduled for the “Now” time, and only keep the time commitment for future time, when generating tasks from a contract?