Can someone explain to me why MRP is delaying the ordering of a part that has fallen below safety stock?
The example below has a safety stock of 130 and NO inventory at time of running MRP (with the Plan Safety Stock checkbox enabled)
The resulting purchase requisition has a wanted date in the future that gives a latest order date beyond the MRP run date - Why?
I would have expected the requisition wanted to be ASAP i.e. Today plus order lead time