Skip to main content

Hello,

My customer want to use planning method N (Next level) for a part. I tested it and it’s working well (supply is created at the release of the demande ) when part is added as component of shop order and on a material requisition.

My issue is that it’s not working (supply is not created at all) when part is added on Work task. Does someone know if it should work and it’s a bug (or a lack of setup) or if it’s normal?

Regards

Anthony

 

Be the first to reply!

Reply