Question

Shop Order SUBCONTRACTING transaction cost calculation

  • 13 January 2022
  • 1 reply
  • 156 views

Userlevel 5
Badge +9

Hello Community,

We are using IFS 9.I have a question for labor and operation trasactions.

 

for subcontracting transaction -WIPFROMSUB normally Material cost is getting added if it is the first subcontracting transaction.

 

But I have found that for 4 transaction there was material cost added in this transaction.

but for last two transactions its manufacturing cost comprises of Material cost plus subcontracting cost.

 

I want to know why this subcontracting cost is getting added particularly for these last two transactions and how it getting calculated.

 

there were two Subcon operations happened .no in-house operation.

so the sequence is 

1st operation -

WIPTOSUB

SUBCONTR

WIPFROMSUB

 

2nd Operation

WIPTOSUB

 

1st operation -

SUBCONTR

WIPFROMSUB

 

 

2nd Operation

WIPTOSUB

 

1st operation -

SUBCONTR

WIPFROMSUB

 

 

2nd Operation

WIPTOSUB

 

 

2nd Operation

SUBCONTR

WIPFROMSUB

 

2nd Operation

SUBCONTR

WIPFROMSUB

 

 

1st operation -

SUBCONTR

WIPFROMSUB     here material cost Plus subcon cost added. before for 1st operation only material cost was present.

I want to know why subcon cost added here and from where it got calculated.

 

Regards,

Deepak


1 reply

Badge +3

Hi,

Subcontracting costs are defined under each cost set in the “Subcontracting Cost” under Engineering → Routing. The costs would be absorbed to the part received from the subcontractor.

 