Hello,
We are trying to calculate our on time delivery for our shop orders. To do this we would like to compare the actual close date to the planned finish date that was entered when the shop order was actually started. Is the “Finish Date” in shop order statistics “locked” when the shop order starts or is it the last recorded finish date? It is not really relevant for us to compare the actual close date to a corrected finish date that updates during the build process.