I was trying to register the Purchase Agreement with backdated entries under ‘Period’ tab. But, system is not allowing to enter any previous dates which lies before sys-date(Current date), in the ‘Valid From’ column. It immediately pops-up an error message, “The Start Date Cannot be earlier than today.”

Any inputs on how to cater this Valid From issue in Supplier Agreement screen, would be highly appreciated.

Regards,

Prabuddha

 

1 reply

Forum|alt.badge.img+28
  • Superhero (Customer)
  • 1482 replies
  • October 12, 2021

Because the Supplier Agreement is only going to be able to have connections to purchase orders going forward in time, you can’t retroactively setup a supplier agreement with dates in the past, it is always a date from today or can be done in the future.  Supplier Agreements require planning ahead to setup when they will start and aren’t designed for past work.