Receive Inventory Parts - Connecting to Project Activity Sequence?

  • June 1, 2023
  • 2 replies
  • 319 views

Forum|alt.badge.img+7
  • Sidekick (Employee)
  • 20 replies

Is it possible to receive inventory parts and connect to a project activity without raising a PO?

 

We cannot seem to achieve this on the Receive Inventory Part screen.

Best answer by Nethmini Kosvinna

 

Hi @Danny ,

You can do following steps to transfer inventory parts to a project inventory.

  1. Receive parts from ‘Receive Inventory Part’ screen.
  1. Then find the stock in the Inventory Part in Stock window. Select Transfer to Project Inventory
  2. You can now enter details of the project and the quantity you want to connect

Hope this will address your requirement.

Thanks & Best Regards,

Nethmini

 

2 replies

Nethmini Kosvinna
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 235 replies
  • Answer
  • June 2, 2023

 

Hi @Danny ,

You can do following steps to transfer inventory parts to a project inventory.

  1. Receive parts from ‘Receive Inventory Part’ screen.
  1. Then find the stock in the Inventory Part in Stock window. Select Transfer to Project Inventory
  2. You can now enter details of the project and the quantity you want to connect

Hope this will address your requirement.

Thanks & Best Regards,

Nethmini

 


Forum|alt.badge.img+7
  • Author
  • Sidekick (Employee)
  • 20 replies
  • June 2, 2023

Perfect, Thank You