Hello everyone,
I have some trouble concerning supplier lead time and I would like some help.
Our customer is on V10 but I recreated the issue on a cloud version.
When a purchase requisition is created by the MRP (planning method C), the "wanted receipt date" is set to today's date. I would like the date to be put back X days later (the supplier have inevitably a lead time).
I tried using the field "Supplier manufacturing lead time" in the "supplier for purchase part".
This value is taken into account but instead of putting back the "wanted receipt date" in the future, this date is set to today's date and the field "Latest order date" is set to the past :
If I manually create a purchase requisition (with the same parameters), the field "Latest order date" is set to today's date and the field "Wanted receipt date" is put back 5 working days later :
Why is the system does not work the same way if the purchase requisition is manually or automatically created ?
Thank you in advance