Dear team,
Is there a reason for not to consume Project Misc Demands by Master Scheduling unless the supply option is PMRP and you run MS for the project? If you have a project misc demand with supply option MRP and the same part is defined as a MS Level 1 part, it does not create supply either by MRP or by MS.