I have a shop order with a lot size of 100. 98 were completed and then we unreceived 1, making the total qty complete now 97. The associated DOP order still thinks there’s 98 complete which I think is creating MRP planned demand for all the components. How do I reduce the qty complete on the DOP order?
+1
No, there are no alarms. I can’t figure out where the MRP planned demand is coming from.