Hi,

 

is there an easy way to get the planning method B parts to MRP Action Proposals list? 

Purchase Reguest is created by INV, based on the B planning method, not MRP. Materials will be delivered to standard inventory.

 

We have Cloud 22R1

br

Miia

 

 

 


1 reply

Userlevel 5
Badge +12

Hi,

You can’t get parts with Planning Method ‘B’ to appear in the MRP Action Proposals list, but you may want to use the ‘Generate Inventory Part Availability Exceptions’ functionality instead.

Run the job from here ….

 

View the results here …

 

Note that this functionality can be used to view Exception Messages for all of the Planning Methods.

I hope that this helps. 