Community,

Since site is the planning level, if we only has one site in IFS, and I cannot plan a purchased part to be replenished by Kanban via ROP, as well as by external supplier via PR?

There is one site currently in our system, but manufacturing building and warehouse are in different locations. We would like this part can be replenished from external supplier via MRP and PR/PO, but when comes to internal replenishment, we would like to replenish by Kanban ROP via transport task.

  1. External supplier replenishment
  2. internal replenishment via Kanban ROP.

I don’t think within one site we could do planning for one part using different replenishment method. kindly share your thoughts here. 

 