Please we need your help. we disabled our IPR in order to use a legacy migrated Planning data as baseline. But when we ran Order Proposal against the legacy Planning data, IFS still calculate a new lot size, new reorder point, new safety stock and entered the legacy lot size , reorder point, safety stock under “previous “ even though the IPR was disabled. Please we do not know how to expalin this . Please help us.