Hi All
I see the following behaviour in IFS and I am thinking whether the behaviour is correct.
I have enabled the following setting in the company level.
Environment - 24R2
Delay Cost of Goods Sold to Delivery Confirmation

I followed following steps.
- Created a customer order with delivery confirmation enabled

- Reserve the customer order and deliver the customer order through a shipment
- OESHIP transactions are not getting created because of the Delay Cost of Goods Sold to Delivery Confirmation setting.
- My assumption was I can create a RMA (Return Material Authorization) and return the part against the order that I delivered. But when I do that its always empty.


I thought its because of the pending delivery confirmation. But I performed the delivery confirmation.
After that I cancelled the previously created RMA and Create a new RMA but still I cannot return the parts.

If this flow works differently when we use Delay Cost of Goods Sold to Delivery Confirmation functionality?
Feels like a bug for me.
Thanks,
Chamath