Hello
We are investigating the planning logic for an inter-site Distribution Order.
Setup
- Demand Site: AB
- Supply Site: ZX
- Supply method: Inter-site Distribution Order
- Route assigned in the Supply Chain Matrix: Friday only
- Internal Transport Lead Time: 4 days
- External Transport Lead Time: 0
- Transport Lead Time: 0
Scenario
A Distribution Order is created with:
- Wanted Delivery Date = 27-Oct-2026 (Tuesday)
The system automatically recalculates:
- Planned Delivery Date = 23-Oct-2026 (Friday)
- Planned Ship Date = 23-Oct-2026 (Friday)
We tested both:
- Customer calendar with weekdays only
- External transport calendar with weekends included
Neither setup affected the calculation.
However, the Planned Receipt Date is still significantly later than the Planned Delivery Date, indicating that the Internal Transport Lead Time is being considered somewhere in the process.
Planned Receipt date - 02-Nov-2026(Monday)
Question
Is it standard behavior that the route is evaluated first and the Planned Delivery Date is adjusted to the nearest valid route occurrence, after which the Internal Transport Lead Time is applied?
Or should the system backward-plan from the Wanted Delivery Date and use the route together with the Internal Transport Lead Time to determine the required shipment date?
In our example, our expectation was that the system would backward schedule from the requested delivery date and calculate a Planned Ship Date of 16-Oct-2026 (Friday) in order to satisfy the Wanted Delivery Date of 27-Oct-2026, rather than moving the Planned Delivery Date itself to 23-Oct-2026.
Could you please clarify whether the observed behavior is standard by design?