Delay Finish date and need date

  • July 18, 2025
  • 4 replies
  • 38 views

Forum|alt.badge.img+3

Hello Guys,

Standard ifs behaviour is that we the finish date is one day before the need date.
Is it possible to delay the need date  per site?
Like finish date: 07/18
need date 07/20

is there a setting in ifs cloud?

Kinds regards

Best answer by Richard Owen

Hi,

Take a look at the Safety Lead Time - depending on how the part is planned, this may give you what you need.

I hope this helps

4 replies

Richard Owen
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • Answer
  • July 18, 2025

Hi,

Take a look at the Safety Lead Time - depending on how the part is planned, this may give you what you need.

I hope this helps


Forum|alt.badge.img+17
  • Superhero (Employee)
  • July 18, 2025

Hi ​@FleVidurK ,

Could you please specify is such dates you are referring are the ones in Shop Order window?

If so, then please post this in the Manufacturing group

Regards,

Pilar


Forum|alt.badge.img+3
  • Author
  • Sidekick (Partner)
  • July 18, 2025

Yes these dates are referring to a shop order window.

Can a moderator move this question to manufacturing please?

kind regards


Forum|alt.badge.img+3
  • Author
  • Sidekick (Partner)
  • July 18, 2025

Hi,

Im talking about these two dates in the shop order window:

 



is there setting which can delay the need date by more than one day.