Hello Guys,
Standard ifs behaviour is that we the finish date is one day before the need date.
Is it possible to delay the need date per site?
Like finish date: 07/18
need date 07/20
is there a setting in ifs cloud?
Kinds regards
Page 1 / 1
Hi,
Take a look at the Safety Lead Time - depending on how the part is planned, this may give you what you need.

I hope this helps
Hi
Could you please specify is such dates you are referring are the ones in Shop Order window?
If so, then please post this in the Manufacturing group
Regards,
Pilar
Yes these dates are referring to a shop order window.
Can a moderator move this question to manufacturing please?
kind regards
Hi,
Im talking about these two dates in the shop order window:

is there setting which can delay the need date by more than one day.