What is the normal process if a configuration needs changing on a customer order line where a pegged purchase order exists?

Is it to cancel the line, recreate, then add the new requisition to the existing Purchase Order, or is there a way the configuration can be changed on the customer order line and replicated on the connected purchase order line?

Cheers,

Jamie

1 reply

Forum|alt.badge.img+1
  • Do Gooder (Customer)
  • June 26, 2026

If have exactly the same Question. The behaviour is strange - I can change the configuration but WIth Applying teh System tells me that the Status needs to be “Completed” what it is already?