Hi All,

We controlled supplier schedule to part XXXXXXXXXXX and find out, that there are displayed 2 Supplier schedules 131, 132- but there should be only supplier schedule 132.
Is there any possibility to change the status of 131 Supplier schedule from transferred to superceeded.

Kindly assist if anyone knows?

Thanks!

Hi @Nisha Gupta 

If you are transferring the supplier schedule via EDI the schedule will receive the Transferred status whenever this step is performed. The schedule can arrive the Superseded status whenever a new supplier schedule is created and run through the schedule flow.