PO has a project connected.
PO has multiple steps for the authorisation done by multiple auth groups.
First group in step1 check if the project connection (and some other attributes) is correct and approves the authorisation first line.
While the order is pending to be authorised by other auth groups in further levels, a user changes the project activity connection (not the entire project) to another activity sequence, which is incorrect.
This causes confusions. Is there any way to stop this from happening?