Hi All,
I have a question about the change management in the supplier schedule.
I create a Material requisition for a part, e.g. Part 01. The requisition’s have 3 lines
- - Part 01 - 10 pc - Due date: 2025.03.10.
- - Part 01 - 10 pc - Due date: 2025.03.11.
- - Part 01 - 10 pc - Due date: 2025.03.12.
I runned MRP for this part, which create the supplier schedule appropriate so I can release and send these lines to the PO.
However when I change the amount (e.g. from 10 to 20) of the first line of the material requisition and run a new MRP it create a new supplier schedule which is very similar to the previous one, just create one more line with the needed 10 pc on !!2025.03.12!! due date, and when I release it and send to the PO, the planned receipt date is 2025.03.12. which is late because I set due date in the material requisition on 2025.03.10 for this line.
How should I set up the system to create these lines with the correct date?
Thank you for your answers!
Roland