Dear All,

 

When we go to “Work Order Structure” in IEE, on “WO Details” tab we can see the work task summary on right hand. (Check Attachment)

When I am checking the same in Aurena, I could not find this “Work Task Summary” in either “Work Order Structure Navigator” screen or in “Work Order Structure Analysis” screen.

Please confirm if we have any other screen in Aurena or this functionality has been removed in Aurena.

 

Thanks in advance!

 

BR

HA

Best answer by Amila Samarasinghe

Hi @imharshit003 Unfortunately this functionality is not yet available in Aurena client

1 reply

Amila Samarasinghe
Superhero (Partner)
Forum|alt.badge.img+14

Hi @imharshit003 Unfortunately this functionality is not yet available in Aurena client