Question

Work Task Dependencies Transfer to Mobile

  • 18 December 2023
  • 1 reply
  • 39 views

Userlevel 2
Badge +5

I am trying to have all dependent tasks from a PM Action transferred to mobile at the same time, so task A must be done before task B can start. However when having task B dependent on task A Finish to Start, task B cannot not be transferred until task A is completed. In this scenario, the tech would have to wait for task B to get transferred before he can start it. I’ve also played around with Combined and Ordered dependencies, but they don’t even seem to have any impact on transfer to mobile, start/complete work as documented in Service Work Preparation - https://docs.ifs.com/ifsclouddocs/23r2/RequestManagement/ActivityAddModifyWorkTaskDependencies.htm. This is 23R1. 


1 reply

Userlevel 7

When you created dependencies, there is a flag called ignore dependencies in execution, or something like that. That same flag also exists on the site. Try that.

Reply