I’ve set up a work task code rule for external customers with a WIP Code and reversal condition of CO Line Invoiced. When I transfer the Work Take Sales line to a CO and invoice, the cost is not reversing unless I do the Manually Release WIP and RMB and select Check and Update Accounting.
I believe the rules will be evaluated when you actually transfer the transactions to finance e.g. when you use Accounting Rules\Voucher\Maintenance Voucher Transfer\Transfer Work Task Time Transactions. Even though the Reversal Conditions say e.g. “Transfer to CO”, all it means is that it will reverse transactions that have been transferred to a CO, when you transfer the transactions to Finance.
I believe the rules will be evaluated when you actually transfer the transactions to finance e.g. when you use Accounting Rules\Voucher\Maintenance Voucher Transfer\Transfer Work Task Time Transactions. Even though the Reversal Conditions say e.g. “Transfer to CO”, all it means is that it will reverse transactions that have been transferred to a CO, when you transfer the transactions to Finance.
Even when I transfer everything and even update to the GL, my wip does not reverse. The only difference is when they are all transferred I didn’t have to select manually release WIP and then do the check and update accounting. This time I just did the check and update and reversed the WIP. But I am expecting it should be doing this automatically, or is this not the case?
I believe the rules will be evaluated when you actually transfer the transactions to finance e.g. when you use Accounting Rules\Voucher\Maintenance Voucher Transfer\Transfer Work Task Time Transactions. Even though the Reversal Conditions say e.g. “Transfer to CO”, all it means is that it will reverse transactions that have been transferred to a CO, when you transfer the transactions to Finance.
Even when I transfer everything and even update to the GL, my wip does not reverse. The only difference is when they are all transferred I didn’t have to select manually release WIP and then do the check and update accounting. This time I just did the check and update and reversed the WIP. But I am expecting it should be doing this automatically, or is this not the case?
Mine did when I tested with Time Transactions. What is the WIP Reversal Condition and WIP Reversal Date?
WIP reversal is event date. Condition is when CO Line Invoiced.
WIP reversal is event date. Condition is when CO Line Invoiced.
Which update are you on? Is this for time transactions or something else?
WIP reversal is event date. Condition is when CO Line Invoiced.
Which update are you on? Is this for time transactions or something else?
Hi
WIP reversal is event date. Condition is when CO Line Invoiced.
Which update are you on? Is this for time transactions or something else?
Hi
And when you run 'Transfer transactions' it doesn't happen? It's odd because it does for me.
WIP reversal is event date. Condition is when CO Line Invoiced.
Which update are you on? Is this for time transactions or something else?
Hi
And when you run 'Transfer transactions' it doesn't happen? It's odd because it does for me.
Hi
WIP reversal is event date. Condition is when CO Line Invoiced.
Which update are you on? Is this for time transactions or something else?
Hi
And when you run 'Transfer transactions' it doesn't happen? It's odd because it does for me.
Hi
No worries. Glad it worked out!