Hi,
Can you please explain what the logic behind the values fetching for the Resource Group LOV when creating 'new work that I will perform' from mobile. How they are filtered and be available in the LOV.
Thank you!
Hi,
Can you please explain what the logic behind the values fetching for the Resource Group LOV when creating 'new work that I will perform' from mobile. How they are filtered and be available in the LOV.
Thank you!
Think those should be the resource groups connected to the logged on mobile user (and valid for the work task site) as the job is to be assigned to the logged on user.
Thanks
Sampath
Hi
Hi Nethmi,
As explained, mobile user should see the RGs which are connected to his resource and valid for the work task site selected in the process when the option “new work that I will perform' is used.
Site Settings tab defines the sites that the resource is able to work on.
Thanks
Sampath