Prepare Work Order Error NOTVENDORRESOURCE: Allocated To 71992 is not connected to Contractor 10310 in Work Task 17900.

  • 15 September 2021
  • 1 reply
  • 65 views

Userlevel 7
Badge +18

When adding a resource to a task in Prepare Work Order on clicking save the user is receiving the following error message:

Allocated To 71992 is not connected to Contractor 10310 in Work Task 17900.

 

Any ideas on how to resolve.

Thank you.

icon

Best answer by RutJWhalen 15 September 2021, 12:23

View original

This topic has been closed for comments

1 reply

Userlevel 7
Badge +18

After looking into this issue.   I have found that there isn’t an issue the Contractor field had been populated on the Task and the resource they were trying to add wasn’t a connected resource.  By removing the Contractor from the Task the user was able to add the required resource.