Skip to main content

Hi,

I have a 3-day work in my MWO.

This is 1 Work Task.

I wish to report every evening the work done - as Intermediate Reporting.

But Today, this is going close/report the Work Task.

So, how to report work done Today without closing hte Work Tasks?

Thank you

Hi,

You can use visits functionality to create multiple assignments for each visit/day according to the work schedule. Once the day’s work is done, you can complete the assignment and update work done on the task. In mobile, technicians work with the assignment, not with the task directly. 

You can keep updating  work done  on task for each day until the task is completely done.

/Uthpala

 


Hi,

sounds a good idea.

Would you have any step by step to setup such visits please?

 

If I follow, I have 1 Work Task (duration 3 days)

I would generate 3 assignemnts? so 3 visits?

Every day, in MWO, I report against a visit and where the Historical Text will be recorded?

 

Thank you / Regards


Hi,

sounds a good idea.

Would you have any step by step to setup such visits please?

 

If I follow, I have 1 Work Task (duration 3 days)

I would generate 3 assignemnts? so 3 visits?

Every day, in MWO, I report against a visit and where the Historical Text will be recorded?

 

Thank you / Regards

You’ll find some more information on how it works here: https://docs.ifs.com/ifsclouddocs/22r2/WorkProcessing/AboutMultipleVisitHandling.htm?StandAlone=true


Finally, I am going to use Debrief and update everyday the info.


Reply