Hello,
While creating a calendar based PM Action with WO generation lead time, the ‘remaining to due’ field is including the weekends as well even though the Maintenance Calendar excludes weekends.
For example: The start date in the maintenance trigger is set to 23/02/2026 and the WO generation lead time is set to 1. The expectation is the Due Date should be considered as 20/02/2026 and automatically generate the WO based on the database task scheduled which does not work.
But in the Maintenance Plan, the remaining to due field shows the number of days as 3 including the weekends. If we have the WO generation lead time as 3, then I’m able to trigger the WO using database task. I believe the due date and remaining to due fields must exclude weekends as per the calendar but can someone please confirm if this is the expected behavior?