Dispatch calendar not showing past assignment

I have a past assignment (May) which is not expected to show in DC gantt chart as its view is from Current date-1 to future, but in DC calendar, since I can select past dates, I am expecting it to show but it does not show up.

on using calendar button from the top, still it does not show

One more task I assigned for 30 may & it does not show

 

Unfortunately, both the Gantt and Calendar only show current day and future days currently. We will look to fix this for the Gantt in a coming release. The calendar will be removed.


Although the option is there on the calendar to go back to past days, both Gantt and calendar will be loaded sys date-1 as the maximum days to past. Hopefully in a future release you will get the possibility to view past data up to a certain no of days in the gantt.