Hi All,

 

When we enter a new cost to a Resource Group, the below error pops up. However, there is no such costs defined for the Resource Group. This has happened even after we creating a new resource group. This behavior is there in one of our environment. Entering cost works fine in our another environment. 

 

 

Anyone, have seen this error?

4 replies

Forum|alt.badge.img+9
  • Hero (Employee)
  • Jun 3, 2026 7:32 AM UTC

Do you get the same problem if the validity period for the costs does not overlap?


kasunhp
Hero (Partner)
Forum|alt.badge.img+10
  • Author
  • Jun 3, 2026 7:42 AM UTC

Do you get the same problem if the validity period for the costs does not overlap?

Yes. I think this is related to a migration script we ran to bring the cost of delivery units to other resource groups. We are investigating this.


Forum|alt.badge.img
  • Do Gooder (Partner)
  • Oct 19, 2026 12:53 PM UTC

Do you get the same problem if the validity period for the costs does not overlap?

Yes. I think this is related to a migration script we ran to bring the cost of delivery units to other resource groups. We are investigating this.

Hi ​@kasunhp , any news please? we are facing similar problem in resource groups.


kasunhp
Hero (Partner)
Forum|alt.badge.img+10
  • Author
  • Oct 19, 2026 4:53 PM UTC

Do you get the same problem if the validity period for the costs does not overlap?

Yes. I think this is related to a migration script we ran to bring the cost of delivery units to other resource groups. We are investigating this.

Hi ​@kasunhp , any news please? we are facing similar problem in resource groups.

How did you create resource groups and assigned standard costs?