Question

Amend 'Actual Hours Worked' in Work Assignment

  • 14 November 2022
  • 1 reply
  • 30 views

Userlevel 4
Badge +11

A user, via MWO, has reported ‘Work I have Completed’ but has incorrectly reported the Start and Finish Dates meaning the ‘Actual Hours Worked’ on the Work Assignment are 100hours more than they should be.

How can I correct this?

 

Thanks, 


1 reply

Userlevel 7
Badge +10

Hi @lisa.gilesAB,

The ‘Actual Work Hours’ is calculated as the difference between ‘Work Start’ and ‘Assignment Finish’. If this is wrong, you can ask for a Data Repair by raising a support ticket. 

Best Regards,
Charana