A user, via MWO, has reported ‘Work I have Completed’ but has incorrectly reported the Start and Finish Dates meaning the ‘Actual Hours Worked’ on the Work Assignment are 100hours more than they should be.
How can I correct this?
Thanks,
A user, via MWO, has reported ‘Work I have Completed’ but has incorrectly reported the Start and Finish Dates meaning the ‘Actual Hours Worked’ on the Work Assignment are 100hours more than they should be.
How can I correct this?
Thanks,
Hi
The ‘Actual Work Hours’ is calculated as the difference between ‘Work Start’ and ‘Assignment Finish’. If this is wrong, you can ask for a Data Repair by raising a support ticket.
Best Regards,
Charana