Consolidate Project / Unique Procurement Project & Non-project purchase of same component

  • January 28, 2020
  • 2 replies
  • 345 views

PRODQ
Superhero (Customer)
Forum|alt.badge.img+17
  • Superhero (Customer)
  • 461 replies

Just looking for any “left of centre” ideas or suggestions, please…

 

We have demand for the same purchased part (same site) from 

  • Projects
  • Projects with purchase req authorisation
  • Customer Orders
  • Shop Orders
  • Material reqs

We run PMRP and MRP which generates the necessary reqs but we’re unable to consolidate the supply onto a single Purchase Order.  You can mix Projects and non-project demand onto a single PO but once the req is a project one that needs purchase authorisation you can’t mix with any other POs…

 

Any ideas gratefully received..

 

Thanks

 

Best answer by MTIMM

We actually had IFS Corp do a custom modification for us to do this exact same thing in IFS8.

View original
Did this topic help you find an answer to your question?

2 replies

MTIMM
Do Gooder (Customer)
Forum|alt.badge.img+3
  • Do Gooder (Customer)
  • 3 replies
  • Answer
  • May 27, 2020

We actually had IFS Corp do a custom modification for us to do this exact same thing in IFS8.


PRODQ
Superhero (Customer)
Forum|alt.badge.img+17
  • Author
  • Superhero (Customer)
  • 461 replies
  • July 13, 2020

Thanks, @MTIMM.

 

Linda

 