Is the demand planning in IFS is taking lead time from SUPPLIER FOR PURCHASE PART or INVENTORY PART?

1 reply

Forum|alt.badge.img+7
  • Hero (Employee)
  • 41 replies
  • April 8, 2025

Demand Planner itself does not use any lead time. It is simply forecast in future period requirements based on past period requirements. It then feeds Master Schedule and MRP that would inevitably utilize the Inventory Part lead time. 