We are running into some issues with our Work Time Calendar and how it translates to Shop Order dates. We currently run two production shifts, 4 days per work (Mon-Thurs) and scheduling to infinite capacity. Our shift hours as as followed: 1st shift = 5:00am to 3:00pm and 2nd = 3:15pm to 1:15am.
We are tying to find a way where transaction dates fall within the start date of the shift, as our 2nd shift hours technically roll into the next day (want midnight - 1:15am hours to count towards the day prior). Since we are scheduling to infinite capacity, it also allows for Friday, from Midnight to 1:15a to be overloaded, from a Shop Order perspective….when we really want Friday as a non-working day and those last hours to count as Thursday.
Are there any systematic options for this, other than adjusting the calendar/schedule to drive what we want but have incorrect data (i.e. remove all hours from Friday)?