Updating Project Connections

  • November 11, 2024
  • 3 replies
  • 63 views

Forum|alt.badge.img+6

Hi 

we frequently run into issues when we need to update a project connection; once a customer order is already released due to this error message.

Has anyone found a way to making changes to get around this error message?.

The need to update is due to the wrong activity having been selected by the user in error. 

3 replies

Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+15

Hi ​@MaggieDP,

 

As the message says, you cannot disconnect the customer order line object once it is released. It is not simple to disconnect this now because when you are Releasing the customer order it actually updates number of records, such as pre-posting the project account details like M103 and M104. So, when disconnecting it is not really easy to reverse all of these updated values.

 

To rectify the user’s mistake, I believe you will have to Cancel the Order Line and re-enter the same line (by duplicating). 

 

 

For the new line user can Connect the correct Activity this time.


Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • November 20, 2024

@MaggieDP As Tharindu explained in his answer, the project connections cannot be updated once the CO is released. He already outlined the action that can be taken. But I know it is very time consuming.

Using incorrect activities are quite common. This often comes up in the implementation projects from the users too. Please raise as an Idea as well in https://community.ifs.com/ideas

There should be a way to modify the connected activities. Of course there can be limitations but at least this should be possible just after the CO is released (Committed state), at least.


Forum|alt.badge.img+6
  • Author
  • Sidekick (Customer)
  • 9 replies
  • November 20, 2024

Thanks for the reply ​@Buddhika Kurera  and ​@Tharindu Illangasinghe 

I created an idea as you suggested, would appreciate your help getting it upvoted !

 

Ability to Update Project connections once line is released | IFS Community


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings