Is it possible to change status of a group of projects simultaneously in projects form?
It is just possible the change status from start to complete one by one.


Is it possible to change status of a group of projects simultaneously in projects form?
It is just possible the change status from start to complete one by one.
Best answer by Buddhika Kurera
The possible options for batch of projects are:
Select set of projects (Status = Initialize) -.Possible status change is Cancel
Select set of projects (Status = Approved) -.Possible status change is Start
Select set of projects (Status = Completed) -.Possible status change is Restart
Hope this helps !