PSO/MSO - Obstructive Work Task not considered in MSO


Forum|alt.badge.img+18

Hi There,

Could someone please help me with this issue. I have created a obstructive maintenance work which can be clearly seen in the both visual shop order operation planning as well as smart manufacturing planning board. This obstructive work is overloading the work center on which the operations are already planned. So, now as per MSO functionality, the operations need to reschedule for the other days where work center is available but this is not happening after finite scheduling and operations are getting loaded on the days of maintenance work.

Also attached the MSO load file for further reference.

 

 

 

Regards,

Mithun K V

Best answer by EqeMithuV

Hi All,

I haven't mention the planned duration in the work task, instead I had only entered planned start date and finish date. After entering the duration on the work task, the obstructive works are considered in MSO.

Regards,

Mithun K V

View original
Did this topic help you find an answer to your question?

4 replies

Forum|alt.badge.img+18
  • Author
  • Superhero (Partner)
  • 392 replies
  • Answer
  • June 23, 2024

Hi All,

I haven't mention the planned duration in the work task, instead I had only entered planned start date and finish date. After entering the duration on the work task, the obstructive works are considered in MSO.

Regards,

Mithun K V


StephanS
Hero (Partner)
Forum|alt.badge.img+8
  • Hero (Partner)
  • 69 replies
  • March 6, 2025

Hi,

I encountered the same issue, but I think I did the right things (apparently I forgot something somehwere...). Can you help me point out what I have missed?

Cheers,
Stephan

 

 

I created the Object, connected it to the Work Center:

 

 

Then I created a Work Task, with Planned Start/End dates and Duration, connected to this Object ID (of the Work Center). Status Released.

 

 

I scheduled the Shop Orders, but I don't see the blocking task in my overview… What am I missing?

 

 


Forum|alt.badge.img+18
  • Author
  • Superhero (Partner)
  • 392 replies
  • March 12, 2025

Hi ​@StephanS ,

Please make sure that your work task is obstructive. This can be indicated against the operational statuses which you can add it to work task under object information

Regards,

Mithun K V


StephanS
Hero (Partner)
Forum|alt.badge.img+8
  • Hero (Partner)
  • 69 replies
  • March 12, 2025

Yeah that worked indeed.