MRP _ Activation without planned task

  • May 22, 2024
  • 1 reply
  • 24 views

Forum|alt.badge.img+4

Hi all, 

 

I am contacting you as, I dont understand how the MRP was activated regarding several inventory parts for several sited :

 

By Mistake, several articles were midstakenly ticked within “MRP Control”

 


 

Purchase requisitions by the MRP have been generated on several companies and sites of my client 

even if  : 

  • Company : “Inventory Part Planning and Replenishment” was unticked 
  • Site : “Inventory Part Planning and Replenishment” was unticked 

So far, the sites have only created and delivered customers orders, material requisitions, Which might be the cause for the MRP proposal, but I thought it would need to have all the above settings ticked and also the scheduled task : “Create order proposal”  

 

What do you think about it ? 

 

Best regards, 

1 reply

PRODQ
Superhero (Customer)
Forum|alt.badge.img+17
  • Superhero (Customer)
  • 469 replies
  • May 23, 2024

You don’t necessarily need a scheduled task.  Someone may have run it manually.  Check Background Jobs and you should see who/when.

 

 