Maintenance Plan date limitation


Forum|alt.badge.img+6

We are using V10 IEE. Our business wants to schedule PM work orders out several years, to 2027. The Maintenance Plan for every PM Action we create will only plan work out to the end of next calendar year, Dec. 2025 in this case. This is observed across multiple sites and calendars used, even when the calendars are generated well past 2027.

How do we get the Maintenance Plan to push planned work out multiple years ahead?

 

 

Best answer by Marcel.Ausan

@acjedynak you need to change the PM_PLAN_HORIZON object property in order to get PM WO beyond 2025.

 

 

I hope this helps.

View original
Did this topic help you find an answer to your question?

2 replies

Marcel.Ausan
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • 1142 replies
  • Answer
  • February 2, 2024

@acjedynak you need to change the PM_PLAN_HORIZON object property in order to get PM WO beyond 2025.

 

 

I hope this helps.


AveTonitM
Sidekick (Partner)
Forum|alt.badge.img+9
  • Sidekick (Partner)
  • 139 replies
  • February 26, 2024

What is the MAINT_PLAN_HORIZON property used for?

 