I created a Separate PM Action, but I can’t figure out how to get IFS to create the Maintenance Plan.  I was able to Manually Generate a Work Order, but I would like to see the plan at lest for the year.  You can see my Maintenance Plan parameters on the attachment.  Please help! 

Best answer by CindyH

Navigate to Maintenance plan in IFS and then extend/shorten plan. You may have to set it out further into the future. You will have to remember to do this every so often. I am on a later version so no screenshot. 

See this post 

 

View original
Did this topic help you find an answer to your question?

2 replies

CindyH
Hero (Customer)
Forum|alt.badge.img+7
  • Hero (Customer)
  • 37 replies
  • Answer
  • August 8, 2023

Navigate to Maintenance plan in IFS and then extend/shorten plan. You may have to set it out further into the future. You will have to remember to do this every so often. I am on a later version so no screenshot. 

See this post 

 


Forum|alt.badge.img+4
  • Author
  • Do Gooder (Customer)
  • 4 replies
  • August 8, 2023

Thank you! 

That fixed my issue!!


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings