Hello,

When I have a released purchase requisition created from MRP that needs authorization, but the authorization step is not executed before MRP run again, the released requisition is getting blowen away and a new planned requisition is created.  Is some set up missing that the released requisition requiring authorization is getting deleted and a new planned requisition created or is this the expected results?

Best, 
Dolly  

1 reply

Forum|alt.badge.img+8
  • Hero (Employee)
  • 33 replies
  • November 2, 2022

Hi,

If you require the Released Purchase requisitions to remain and be included as supply for MRP you need to check the below setting on Site/ Manufacturing Tab 

 

 

 

This will ensure that any ‘Released’ po’s are not deleted when re planning processes.

 