Does anybody know the formula  in Risk Analysis for “Calculated Risk Estimate” based on 3-point method in IFS?

 

1 reply

Forum|alt.badge.img+8

Hi @womich,

For 3 – Point Analysis, Calculated Cost = weighted average of Min, Most Likely and Max

The weighted average is equal to [(Min estimate) x (Analysis Min Weight Factor) + (Most Likely estimate) x (Analysis Norm Weight Factor) + (Max estimate) x (Analysis Max Weight Factor)] / [(Analysis Min Weight Factor) + (Analysis Norm Weight Factor) + (Analysis Max Weight Factor)]

Hope this will helps you. If you have further concerns please raise a community question to Products (Manufacturing, Products, Engineering)

 