Work Order and Procject Connection

  • October 13, 2021
  • 1 reply
  • 145 views

Forum|alt.badge.img+9

Could you help to advice the functionality behind below?

Try to connect a work order to an activity, and then verify that the dates are transferred from the activity to the work order.
Early start/late finish dates are not fetched in WO.

 

Regards,

Peshala.
 

Best answer by Thommy

These dates have never been transferred over to WO from a connected activity.

However I know that this has ben requested from customers in the past, but haven’t been prioritized. 

1 reply

Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • 204 replies
  • Answer
  • October 13, 2021

These dates have never been transferred over to WO from a connected activity.

However I know that this has ben requested from customers in the past, but haven’t been prioritized.