When working with the PNG, what is the purpose of setting it to Closed rather than leave it in Executed Status

  • Nov 23, 2026 3:58 PM UTC
  • 1 reply
  • 9 views

Forum|alt.badge.img+13

When working with the PNG, what is the purpose of setting it to Closed rather than leave it in Executed Status?  

Thank you 

Patrick

1 reply

Forum|alt.badge.img+5
  • Do Gooder (Employee)
  • Nov 25, 2026 3:52 PM UTC

Hi ​@PIreland,

 

Quick clarification first: Executed and Closed are statuses on the Material Transfer Requisitions (MTRs) that MPMRP creates for the PNG, not on the PNG itself.

Based on that:

*Executed means the transfer has happened. The parts and their cost have moved from the issuing PPSA to the receiving PPSA.
*Closed means the MTR is done. The docs say "the MTR process is finished and no further action is required."


So closing doesn't move any stock or cost. That already happens at Execute. Closing is the sign-off step:

*Executed MTRs are still waiting for review. Closed MTRs are finished. If you filter on Executed, you get a clean worklist of what still needs checking.
*It's the intended end state. If Automatic MTR is set on the PNG, Inventory-sourced MTRs are taken all the way to Closed automatically. You only close MTRs by hand when they were processed manually.

 

Hope this helps,

Gleb