I am trying to book contractor's time against a PO. In EE I can use the Project Time Registration screen but in Aurena I can not find the equivalent screen, where I can enter a PO Number.

If you type Project Time Registration in the navigator for Aurena you are directed to Quick time Reporter but you do not have the option to enter a PO Number.

If you use time registration you also don’t have the option to book against a PO.

As a workaround, I am using the Project Transaction Screen.   

 

Need to turn this setting on 

 