Hi Kumiko,
The progress and calculation can be different based on the progress method that you are using in the Activity as well as the process you are using to handle the DOP supplies.
Are you using separate POs in the activity to provide the supplies for the DOP?
Thanks and Regards,
Pradeep
@Kumiko Not sure if I get your questions correct.
However the Earned Value is calculated as
Earned Value = Progress of the activity * Planned Cost (or Baseline Cost depending on your selection)
It cannot be entered manually.
In your first screen capture I can see the Progress as 25% and Planned Cost as 1,680,000. So the EV is 420,000 (as per the equation). But in the next screen capture EV is 0 probably because the Progress is 0 (please check).