Skip to main content

What is the correct value to put in Earned Value Cost?
I have created a DOP header connected to PJ.
Depending on the Structure Depth setting, the Earned Value Cost value is different.

Please let me know what value should be set for Earned Value Cost.

 

Pattern A:DOP Parts. Earned Value Cost is 420,000

PatternB:Full Level  Earned Value Cost is null(0)

 

Hi Kumiko,

The progress and calculation can be different based on the progress method that you are using in the Activity as well as the process you are using to handle the DOP supplies.
Are you using separate POs in the activity to provide the supplies for the DOP?

Thanks and Regards,
Pradeep

 


@Kumiko Not sure if I get your questions correct.

However the Earned Value is calculated as

Earned Value  = Progress of the activity * Planned Cost (or Baseline Cost depending on your selection)

It cannot be entered manually.

In your first screen capture I can see the Progress as 25% and Planned Cost as 1,680,000. So the EV is 420,000 (as per the equation). But in the next screen capture EV is 0 probably because the Progress is 0 (please check).


Reply