Unable to attach at Task Template to a Work Task Plan

  • May 7, 2025
  • 1 reply
  • 12 views

Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • 10 replies

I am unable to attach a Task Template ID to a Work Task Plan in Project Deliverables.    I have connected the Template ID to Technical Class = % in Work  Task Template Connections.  My project deliverable line is for an inventory part which includes a Technical Class.  I do not know why I am unable to select a Task Template ID from on the Work Task Plans tab.  Is there somewhere else it is defined?

1 reply

Forum|alt.badge.img+5
  • Do Gooder (Employee)
  • 11 replies
  • May 15, 2025

Hi,

You need to connect the Project Deliverable Item to a Technical Class rather than the part. Then "Copy Work List from Work Task Template” button will be available in Planning Items tab.

Best regards,

Nebahat