Skip to main content

It seems that when I create a Shop Order within Project Deliverables that the system automatically sets the Supply Type for the Material to Project Inventory.  Is there a way to define the parts or setup the system so that we can use standard inventory for the shop order material?

 

Thank you

Patrick

Hi, 

You can use the supply option MRP for the materials if you are referring to the standard inventory. 

Regards,

Sasika


Reply